In
order to execute the project, Partner will establish the project
task force team such as Engineering an Management Team in head
office and construction and site Acquisition Management Team
in center of each area, which will advise later.The Project
Team headed by the Project Manager will control the said team
timely, quality, reliability and efficiently.The following subsection
describes highlights of Partner planed approach to he execution
activities required for the Project.
Project
schedules shall be submit to OWNER after the company has negotiated
contract agreement
3.
Project Engineering Team
|
Project
Engineering and Administration performed for the project shall
consist of defining, planning, coordination and checking overall
schedule.a) Engineering and Drafting
Engineering Team shall design to comply with standard and code
that correspondence to customer, standard Drawing and calculation
need shall be provide. The following is some drawing to be provide.
3.1 Site Mapping
3.2 Tower
3.3 Side View
3.4 Tower Elevation
3.5 General Arrangement of Tower
3.6 Antenna Mounting Detail
3.7 Equipment Layout Plan
3.8 Single Line Diagram
3.9 Etc.b) Planning & Scheduling of Project
Planning & Schedule engineer shall work closely the project.
He will monitor and control project to meet schedulec) Material
Managementd) Cost Control (Accounting, Payment, etc)e) Document
for payment (invoice etc.) & Weekly Report etc.Weekly report,
which shows project progress, shall be provided to OWNER every
week.
4.
Project Site Preparation Team |
Site preparation team shall performed to complete civil work,
tower, electricity installation, lighting system, grounding
system, cable ladder, air-conditioning, alarm, site security
system and all relevant.The temporary facilities (office, stockyard,
etc.) and work forces for construction will distribute and manage
as follow: -a) Temporary Facilities
If Client supplied area for temporary facility in client's estate
area, in cas we will provide the one temporary facility such
as site office, material stockyard & shop yard etc.If not
available, one temporary facility will provide at the center
of each project area.b) Work crew for Site Preparation work
will plan as follow: -
Tower Installation One Team (per site)
- Tower erection crew
-Tower painting crew
- Grounding and Lighting work crew
Equipment Room One Team (per site)
- Civil/Building work crew
- Electrical work crew
- Other work crew
5.
Project Installation TeamInstallation Team |
shall
install and commissioning of Radio & Microwave equipment,
which supplied by OWNER
Indoor Installation One Team (per site)
- Antenna Installation crew
- Feeder running crew
- BTS installation crew
shall
be assist for obtaining permits and approval by Government authorities
or agencies for Site Preparation and Installation Work.a) Site
Preparation (Bangkok Area)
Permission document shall be submitted for information to Civil
Department of Local Government for each area incases of building
not over 4 stories if not shall submitted to Head Office of
Civil Department of Bangkok Metropolitanb) Site Preparation
(Other Area)
Permission document shall be submitted for information to Sub-district
of each area.c) Road Permission
In case of planning to join a new road from base station site
to existing high way, the permission document shall be submitted
to High Way Department.d) Electrical Application
For Bangkok, Samutprakarn, Prathumthani and Nonthaburi area
the application shall be performed at MEA (Metropolitan Electricity
Authority) if not shall be at PEA (Provincial Electricity Authority.)
7.
Material Management Plan |
Material
Management shall be carried-out by Engineering Group in Bangkok
Head Office. Material Management shall be carried out to obtain
and evaluate competitive bids form Qualified vendor for the
equipment and materials, which are to be furnished in accordance
with the timing established by the project schedule.Material
Management shall consist of the following documents and reports
being prepared: -
1. Equipment and Material Bidders list
2. Material Requisition and Specification
3. Request for Quotation
4. Bid evaluation and recommendations
5. Purchase Requisition and Other
6. Checking of Material Delivery Schedule, Inspection &
Expedition of Material
7. Delivery Notice to Site Office
Notices
and ReportMaterial Control at Job Site shall consist of the
followings: -
1. Receiving Inspection
2. Material Storage (Warehouse and/or Open Area)
3. Inventory Control
4. Material Identification
5. Material Distribution
6. Material Handing
|